Through the final stages of the Rail Network Rebuild (RNR) we are delivering critical rail network upgrades before City Rail Link opens in 2026. These will support cuts in journey times, fewer delays and trains every 4-5 minutes at peak.
The rebuild replaces old foundations under tracks and upgrades drainage, allowing more reliable train journeys and helps prepare the network for City Rail Link.
The work involves removing the existing tracks and digging down up to a metre to replace the aging rock foundations under the tracks, replacing ballast and upgrading drainage to improve rail’s resilience to flooding.
The final stages of RNR complete our upgrade of the priority areas across the network, enabling an efficient rail network that can accommodate the increased level of services that comes with CRL.
Additional funding provided by the Government in the latest Budget ($159.2m) has allowed us to move forwards with certainty to plan and deliver much-needed upgrades on the rail network. These are essential to enable the faster, more frequent journeys that CRL and the other major projects we are delivering will bring.
We also received a further $48.8 million for upgrades to the Auckland network. These two funding pots are being wrapped into one delivery programme under RNR – to ensure the most effective, efficient delivery.
The majority of the final stages of the Rail Network Rebuild will be delivered in extensions to the usual closures when all services are suspended during major holidays so our teams can safely work on the tracks and inside tunnels. This included four weeks over Christmas 2024, and will include a couple of extended blocks around Easter 2025 (12-27 April) and Christmas 2025 with some shorter periods of single line running. A full network closure may not be needed for all those blocks, but this is the maximum time needed. There is also some contingency allowed throughout the programme for unexpected events.
We know it’s vital to get the most out of this time period. That’s why we will be working 24-7 wherever possible. The hard work being achieved through Rail Network Rebuild is delivering a decade’s worth of work over 18 months - ultimately this will enable more efficient and faster train services. We thank commuters, passengers and freight customers for their patience with these disruptions as we safely deliver the huge amount of work.
This approach means relatively short sharp closures and less ongoing disruption when passengers and freight suppliers need the network most.
We are working hard with Auckland Transport to retain weekday peak services so Aucklanders can still rely on the train for their weekday routines. This means, wherever possible, outside major holiday periods, rail line closures will be at weekends or late evenings and have school holidays as planned contingency periods to support the programme being delivered on-time.
Our focus with AT, as we planned how to deliver this work, has been on working as effectively and efficiently as possible to reduce disruption to customers - we are trying to keep trains running for as many people and goods as possible, as often as we can, but sometimes we must close the network for safety and to get work done more quickly.
To find out more about public transport options during these works, customers can visit AT’s Journey Planner or to the AT Mobile app.
Customers can also view the train line status page on the AT website.
Find out where our teams are working and what we are doing here.
Without suspending frequent commuter services, it would be impossible to safely use much of this time-saving technology.
Rail Network Rebuild related documents proactively released under the Official Information Act.
Full upgrade and renewals works were completed over 2024-25 summer rail closure while the line was closed for electrification. The newly electrified 19km of rail line between Papakura and Pukekohe is now open. Electric passenger trains are now running all the way to the city centre with no need to change trains at Papakura.
The focus of Easter RNR works will mostly be on priority areas of the Southern Line between Ōtāhuhu and Papakura, including a 1.2km stretch along both sides of Hospital Road, south of Middlemore Hospital.
Later in the year, RNR teams will also be working on sections between Newmarket and Waitematā (Britomart) and on the Western Line between Newmarket and Avondale, and between Henderson and Swanson.
The Rail Network Rebuild is challenging:
Wherever possible we’ll also do proactive maintenance – such as replacing sleepers and trimming vegetation that would otherwise need to be dealt with in the coming years – and using the line closures to complete other rail related projects.
All railways require ongoing maintenance but we are thinking ahead and trying to avoid the need to come back and cause further disruption in the years ahead.
These photos illustrate some of the different types of work that go into the Rail Network Rebuild (RNR) .
Rail Network Rebuild work involves removing track and digging out the original formation (foundation), adding stabilizing mesh, putting in and compacting new formation, then replacing the rails and sleepers and then re-ballasting. This example at Sylvia Park includes adding a new crossover, which will improve flexibility on the network.
To renew formation quickly, KiwiRail is using a range of specialist machines and technology. These include:
The panel lifter can pick up and put down up to 75 metres of straight sections of track and sleepers at a time.
Stabilisers shake and consolidate the track formation, to ensure new formation is stable.
Tamper machines measure the track placement, lift it, and pack the ballast underneath to hold it in place. It helps create a smoother ride for passengers and freight.
Rail grinders smooth irregularities in the tracks and restore their profile, so they last longer. It also helps to improve the ride for passenger and freight services.